SBMO schreef op 18 november 2013 20:32:
Hello,
Sometimes it helps just contacting parties concerned:
Encana:
Hello. Thank you for your inquiry to Encana's Deep Panuke natural gas project. Commissioning continues offshore at Deep Panuke. This planned shut-in of the wells is part of the commissioning process. The shut-in is expected to last approximately two weeks. Following the shut-in, the wells will be brought back on line. The goal overall is to get the full capacity of 300 MMscf/day.
Hoping that this information helps to answer your inquiry.
Regards,
SBM:
Thanks for your e-mail. We are currently working towards debottlenecking the system in order to ramp up to full production capacity of 300MMcf/d. Once we have reach that level of steady state production, we will begin a 72 hour test which will lead to Production Acceptance Notice (PAN). Once we have received PAN we will be officially on hire and will make an announcement to the markets.
Hope this helps.
All the best,
Nicolas Robert
HEAD OF INVESTOR RELATIONS
Main: +377 9205 1500
Direct: +377 9205 1898
nicolas.robert@sbmoffshore.comWebsite:
www.sbmoffshore.comSBM Offshore